| The total water spray volume of the system (tons/hour) | 
						Amount of water wasted each year/tons 
						(Assuming 15% waste) | Annual wasted water bill | 
| 1.2 | 1,120.0 | 896.0 | 
| 2.4 | 2,250.0 | 1,800.0 | 
| 12 | 11,230.0 | 8,984.0 | 
| 24 | 22,460.0 | 17,968.0 | 
| 120 | 112,300.0 | 89,840.0 | 
| The total water spray volume of the system (tons/hour) | The amount of water wasted each year, 15% of the ton is assumed to be wasted | Electricity wasted per year (KW) 3 bar | 3 bar of electricity lost every year | Electricity wasted per year (KW) 100 bar | Electricity lost every year (yuan) 100 bar | 
| 1.2 | 1,120 | 129 | 10 | 4,280 | 3424 | 
| 2.4 | 2,250 | 258 | 21 | 8,560 | 6848 | 
| 12 | 11,230 | 1,290 | 103 | 42,800 | 34240 | 
| 24 | 22,460 | 2,580 | 206 | 85,600 | 68480 | 
| 120 | 112,300 | 12,980 | 1032 | 428,000 | 34,2400 | 